Today: 2026-08-30
- F2 vanities, shower bases, W/D + heater specs measurable on siteGates: F2 DIM → the whole DWV batch2Days left09/01/2026 Tue
- AS-F1 second-bathroom decisionGates: PM's AS1 batch starts 9/9 — last cheap window4Days left09/03/2026 Thu
- Astoria electrical + plumbing packages orderedGates: AS rough batches Wk1–25Days left09/04/2026 Fri
- Con Ed service check for Astoria electrificationGates: only item nobody on the crew can accelerate5Days left09/04/2026 Fri
- F2 countertop — order off the F3 templateGates: F2 CTP ~Sep 305Days left09/04/2026 Fri
- F2 grilles (48x8, 30x8, 8x16) + 10" duct kitGates: F2 VNT Wk212Days left09/11/2026 Fri
- F2 tile + waterproofingGates: F2 TIL Wk3–419Days left09/18/2026 Fri
- F2 cabinets · LVP (48h acclimation) · devices + fixturesGates: F2 finish week26Days left09/25/2026 Fri