Renovation Board
5 W 126th St · 2812 Astoria Blvd
Read-only

Every batch appears 2 business days before it starts: order/stage its material by the stage-by date.

Stage byStartsUnitBatchCrew this week
08/31/2026 MonSTAGE NOW09/02/2026 WedF1F2+F1 DWVCharlie
08/31/2026 MonSTAGE NOW09/02/2026 WedF1F2+F1 DWVGarami Zoli
08/31/2026 MonSTAGE NOW09/02/2026 WedF3F3 PNT finishMiguel
08/31/2026 MonSTAGE NOW09/02/2026 WedF2F2 FRM startThomas
08/31/2026 MonSTAGE NOW09/02/2026 WedF2F2 haul outZoli
08/31/2026 MonSTAGE NOW09/02/2026 WedASElectrician service upgrade estimate (AS)Csaba
09/01/2026 TueSTAGE NOW09/03/2026 ThuF2F2 FRMThomas
09/01/2026 TueSTAGE NOW09/03/2026 ThuAS1AS1 DEM punchZoli
09/01/2026 TueSTAGE NOW09/03/2026 ThuASAS walk + ELR listCsaba
09/02/2026 WedSTAGE NOW09/04/2026 FriF1F2+F1 DWV · stack tie-inCharlie
09/02/2026 WedSTAGE NOW09/04/2026 FriF3F3 PNT touchMiguel
09/02/2026 WedSTAGE NOW09/04/2026 FriF1F2+F1 DWV · cap+holdGarami Zoli
09/02/2026 WedSTAGE NOW09/04/2026 FriAS1AS1 haul + MATZoli
09/02/2026 WedSTAGE NOW09/04/2026 FriF3F3 ETR outlets/switchVillmos
09/02/2026 WedSTAGE NOW09/04/2026 FriASAS ELR orderCsaba
09/03/2026 Thu09/07/2026 MonF2F2 gas + WSR layoutCharlie
09/03/2026 Thu09/07/2026 MonF1F2+F1 DWV pressure testGarami Zoli
09/03/2026 Thu09/07/2026 MonF2F2 FRM wet wallsThomas
09/03/2026 Thu09/07/2026 MonAS1AS1 haul outZoli
09/03/2026 Thu09/07/2026 MonAS1AS1 MAT stageMiguel
09/03/2026 Thu09/07/2026 MonF3F3 TST + CVR → F3 DONEVillmos
09/07/2026 Mon09/09/2026 WedF2F2 WSRCharlie
09/07/2026 Mon09/09/2026 WedAS1AS1 DIMGarami Zoli
09/07/2026 Mon09/09/2026 WedF2F2 FRMThomas
09/07/2026 Mon09/09/2026 WedF2F2 FRM assistZoli
09/07/2026 Mon09/09/2026 WedF1F1 ELR (fan/GFCI)Villmos
09/08/2026 Tue09/10/2026 ThuAS1AS1 DWVGarami Zoli
09/08/2026 Tue09/10/2026 ThuF1F1 CLS prepMiguel
09/08/2026 Tue09/10/2026 ThuF2F2 ELR.AVillmos
09/08/2026 Tue09/10/2026 ThuASAS ELR.A panelsCsaba
09/09/2026 Wed09/11/2026 FriASAS ELR.ACsaba
09/10/2026 Thu09/14/2026 MonF1F2 WSR + F1 WSRCharlie
09/10/2026 Thu09/14/2026 MonAS1AS1 DWVGarami Zoli
09/10/2026 Thu09/14/2026 MonF2F2 VNT ductsThomas
09/10/2026 Thu09/14/2026 MonAS2AS2 DEM punchZoli
09/10/2026 Thu09/14/2026 MonAS2AS2 MATMiguel
09/10/2026 Thu09/14/2026 MonF2F2 ELR.BVillmos
09/10/2026 Thu09/14/2026 MonASAS ELR.ACsaba
09/11/2026 Fri09/15/2026 TueF2F2 HVC linesetsCharlie
09/11/2026 Fri09/15/2026 TueF2F2 VNT + grillesThomas
09/11/2026 Fri09/15/2026 TueAS2AS2 haulZoli
09/11/2026 Fri09/15/2026 TueAS1AS1 MATMiguel
09/11/2026 Fri09/15/2026 TueAS1AS1 ELR.BCsaba
09/14/2026 Mon09/16/2026 WedAS1AS1 WSR (Charlie)Charlie
09/14/2026 Mon09/16/2026 WedF2F2 VNT 10" ductThomas
09/14/2026 Mon09/16/2026 WedF1F1 CLS boardZoli
09/14/2026 Mon09/16/2026 WedF1F1 PLSMiguel
09/15/2026 Tue09/17/2026 ThuF2F2 TST-RCharlie
09/15/2026 Tue09/17/2026 ThuF2F2 gate punchThomas
09/15/2026 Tue09/17/2026 ThuF2F2 ELR.C + TST-RVillmos
09/16/2026 Wed09/18/2026 FriF2F2 gate closeCharlie
09/16/2026 Wed09/18/2026 FriF2F2 CLS prepThomas
09/16/2026 Wed09/18/2026 FriF1F1 CLSZoli
09/17/2026 Thu09/21/2026 MonF2CLS·PLS · HVC condenser→backyard (Charlie)Charlie
09/17/2026 Thu09/21/2026 MonF1SND·PNT (Miguel) · HVC yard condensers (Charlie)Charlie, Miguel
09/17/2026 Thu09/21/2026 MonAS1HVC linesets·TST-R·CLS·PLS--
09/17/2026 Thu09/21/2026 MonAS2DIM·DWV (Garami Zoli)Garami Zoli
09/24/2026 Thu09/28/2026 MonAS2AS2 ELR electrical rough (Csaba)Csaba
09/24/2026 Thu09/28/2026 MonAS2AS2 HVC split-AC linesetsCharlie
09/24/2026 Thu09/28/2026 MonAS2AS2 WSR water supply rough (Charlie)Charlie
09/24/2026 Thu09/28/2026 MonF2SND·PNT1·TIL·CAB·CTP · HVC heads+commission--
09/24/2026 Thu09/28/2026 MonF1TIL·vanity·PTR·ETR · HVC line-hide+heads--
09/24/2026 Thu09/28/2026 MonAS1SND·PNT1--
09/24/2026 Thu09/28/2026 MonAS3DEM punch·DIM--
10/01/2026 Thu10/05/2026 MonAS3AS3 DWV (Garami Zoli)Garami Zoli
10/01/2026 Thu10/05/2026 MonF2FLR·PTR·ETR·TST·CVR → DONE Oct 2–9--
10/01/2026 Thu10/05/2026 MonF1TST·CVR → DONE--
10/01/2026 Thu10/05/2026 MonAS1TIL·CAB--
10/01/2026 Thu10/05/2026 MonAS2CLS·PLS--
10/06/2026 Tue10/08/2026 ThuAS3AS3 WSR (Charlie)Charlie
10/08/2026 Thu10/12/2026 MonAS1FLR·trim·HVC heads·TST → DONE ~Oct 16--
10/08/2026 Thu10/12/2026 MonAS2SND·PNT·TIL--
10/08/2026 Thu10/12/2026 MonAS3ELR (Csaba)·HVC linesets·CLSCsaba
10/15/2026 Thu10/19/2026 MonAS2CAB·FLR·trim·HVC heads → DONE ~Oct 30--
10/15/2026 Thu10/19/2026 MonAS3PLS·PNT·TIL·HVC heads·finish → DONE ~Nov 13--

Material gates (hard deadlines)

  • 09-01 -- F2 vanities, shower bases, W/D + heater specs measurable on site (F2 DIM → the whole DWV batch)
  • 09-03 -- AS-F1 second-bathroom decision (PM's AS1 batch starts 9/9 — last cheap window)
  • 09-04 -- Astoria electrical + plumbing packages ordered (AS rough batches Wk1–2)
  • 09-04 -- Con Ed service check for Astoria electrification (only item nobody on the crew can accelerate)
  • 09-11 -- F2 grilles (48x8, 30x8, 8x16) + 10" duct kit (F2 VNT Wk2)
  • 09-18 -- F2 tile + waterproofing (F2 TIL Wk3–4)
  • 09-04 -- F2 countertop — order off the F3 template (F2 CTP ~Sep 30)
  • 09-25 -- F2 cabinets · LVP (48h acclimation) · devices + fixtures (F2 finish week)