Project timelinecommitted = solid · proposed, subject to adjustment = dashed
| F1 | DWV DWV MISC MISC DWV DEM DWV MISC | DWV CLS ELR | WSR CLS CLS PLS | SND 0/3 | TIL 0/5 | TST 0/2 | ||
|---|---|---|---|---|---|---|---|---|
| F2 | MISC DEM FRM FRM DEM MISC | WSR WSR FRM FRM FRM ELR | HVC TST-R MISC VNT VNT VNT MISC CLS ELR ELR | CLS 0/3 | SND 0/6 | FLR 0/5 | ||
| F3 | PNT PNT ETR | TST | ||||||
| AS1 | DEM MISC | MISC DWV MISC MISC | DWV WSR MISC ELR | HVC 0/4 | SND 0/2 | TIL 0/2 | FLR 0/4 | |
| AS2 | DEM MISC MISC | DWV 0/2 | WSR 0/3 | CLS 0/2 | SND 0/3 | CAB 0/4 | ||
| AS3 | DEM 0/2 | DWV 0/2 | ELR 0/3 | PLS 0/5 |
Week 0 · 2026-08-31
committedMISC x8Tap any dotted code for its meaning
| Mon 8/31 | Tue 9/1 | Wed 9/2 | Thu 9/3 | Fri 9/4 | |
|---|---|---|---|---|---|
| Charlie | |||||
| Plumbing Master | |||||
| Viamarche | -- | -- | -- | -- | |
| Father-in-law | -- | -- | -- | ||
| Thomas | |||||
| Zoli | |||||
| Miguel |
Legend
- DEM
- demolition
- haul
- debris removal to dumpster
- MAT
- receive + stage materials by room and trade
- DIM
- measure the real fixture, mark centerlines
- FRM
- framing: partitions, closets, blocking, openings
- DWV
- drain–waste–vent rough plumbing + pressure test
- WSR
- water supply + gas rough (valves, T&P, pan drain)
- ELR.A
- electrical: panels + feeders
- ELR.B
- electrical: boxes + cable, circuit # both ends
- ELR.C
- electrical: terminations + directory
- VNT
- exhaust ducts, caps, laundry grilles + 10" duct
- HVC
- split-AC: linesets/condensate rough; condensers; heads after paint; commission
- TST-R
- ROUGH-IN GATE test — nothing closes before it
- CLS
- close walls
- PLS
- plaster + tape
- SND
- sand to paint-ready
- PNT
- prime + coats
- TIL
- tile; grout next day
- CAB
- cabinets on subfloor (never on floating floor)
- CTP
- countertop (F2 fabricated off F3 template)
- FLR
- floating LVP AFTER cabinets; tile floors before fixtures
- APP
- appliances set + connected
- PTR
- plumbing trim: toilets, faucets, shower trim
- ETR
- electrical trim: outlets, switches, fixtures — after paint
- TST
- full tests: every fixture, every breaker tripped
- CVR
- cover plates ONLY after tests pass
- TUP
- touch-up + final clean